BluePad supports the Losange group (consortium made up of the NGE group and the telecoms operator Altitude Infrastructure among others), in charge of the deployment of fibre optic in the Grand-Est region. An operation allowing the connection of nearly a million outlets by 2023, in 3,600 municipalities in the region.

By taking advantage of the high level of adaptability of the basic BluePad solution, the R&D teams have developed, in collaboration with the Losange work teams, a personalised solution specifically adapted to the problems and the measure of this large-scale project.

The LOSANGE teams, their partners and subcontractors, now have a common and transversal solution to monitor and control the progress of the deployment in real time.